CONSTRUCTION UPDATE: Health Science Education Complex – Feb. 17 Exterior utility work is mostly complete, and crews are finishing interior framing and rough-in work. Interior finishes are beginning to be installed, and furniture selection has also started, said Project Manager Michael Cremers. Installation of audio and visual equipment for classrooms is also underway. Work remains on schedule, with completion scheduled for July 1. Project: Health Science … [Read more...] about CONSTRUCTION UPDATE: Health Science Education Complex – Feb. 17
Construction Update
CONSTRUCTION UPDATE: Health Science Education Complex – Dec. 23
Construction Update – December 23 Work remains on schedule, and the building is enclosed for the winter, allowing workers to focus on interior work. “We have temporary heat in the building for the interior finishes. As the building sits right now, we have approximately 70 percent of the interior framing in place and drywall is right behind that,” said Lee McQueen, UNK director of facilities, management and planning. Crews are hanging drywall on the north end of the … [Read more...] about CONSTRUCTION UPDATE: Health Science Education Complex – Dec. 23
CONSTRUCTION UPDATE: Health Science Education Complex
Project: Health Science Education Complex Site Location: Corner of Highway 30 and University Drive, west edge of UNK campus Cost: $19 million. Size: 23,000 square feet on two levels Construction Start: April 4 Planned Completion: June 2015 About The Project: A collaboration between University of Nebraska Medical Center and University of Nebraska at Kearney, the complex is being built to meet growing demands for primary and rural health care. … UNK and UNMC … [Read more...] about CONSTRUCTION UPDATE: Health Science Education Complex